Flashcards · Project Management
PRINCE2 Practitioner Flashcards
Free flashcards for the PRINCE2 7 Practitioner exam: flip each card to reveal the definition. Built from our PRINCE2 7 Practitioner glossary, they cover the principles, roles, management products and terms that scenario questions turn on - study aids, not exam content.
1 / 50
Click the card (or press Space) to flip · use Prev/Next to move
All 50 terms
- Apply and tailor
- The Practitioner-level skill: use the method correctly in a scenario and adapt it to the project's context.
- Five integrated elements
- People, principles, practices, processes and project context - the frame of PRINCE2 7.
- Project ecosystem
- The project team, its surrounding organisation, and external parties whose interests and culture shape the project.
- Ensure continued business justification
- Principle: a project needs a valid reason to start and continue; if it disappears, escalate - closing early is legitimate.
- Learn from experience
- Principle: seek lessons at the start, record them during the project, pass them on at the end.
- Defined roles, responsibilities and relationships
- Principle: an agreed structure where everyone knows who directs, who manages and who delivers.
- Manage by stages
- Principle: the board commits funding one management stage at a time, reviewing at each boundary.
- Manage by exception
- Principle: manage freely within agreed tolerances; escalate when a tolerance is forecast to be exceeded.
- Focus on products
- Principle: agree what will be delivered, and to what quality, before planning the work.
- Tailor to suit the project
- Principle: adapt the method to size, risk and environment - without ever dropping a principle.
- Sustainability (performance aspect)
- Managed with targets and tolerances in PRINCE2 7, alongside benefits, cost, time, quality, scope and risk.
- Output
- The product a project delivers - what changes hands at handover.
- Outcome
- The change in ways of working that the output enables once people use it.
- Benefit
- The measurable improvement resulting from an outcome, judged against the business case.
- Dis-benefit
- An actual negative consequence of the change, knowingly accepted and managed alongside the benefits.
- Benefits management approach
- Defines how, when and by whom benefits will be measured - often continuing after project closure.
- Project board
- The directing level: executive, senior user and senior supplier, accountable to corporate management.
- Executive
- Owns the business case; the board's single point of accountability and ultimate decision-maker.
- Senior user
- Represents product users; specifies the benefits and is accountable for showing they are realised.
- Senior supplier
- Represents those who design, build and deliver the project's products.
- Project manager
- Runs the project day to day on the board's behalf, within delegated tolerances.
- Team manager
- Accepts and delivers work packages, reporting progress via checkpoint reports.
- Project assurance
- The board's independent check that the project is run properly - never delegable to the project manager.
- Change authority
- Person or group delegated change decisions within limits, usually funded by a change budget.
- Project support
- Administrative help for the project manager and teams: registers, logs and records.
- Product-based planning
- Define the products and their descriptions first, then derive the activities to build them.
- Project product description
- Defines the overall product, the customer's quality expectations and the project's acceptance criteria.
- Product description
- Defines one product: purpose, composition, quality criteria and how it will be checked.
- Stage plan
- The project manager's day-to-day control plan for a single management stage.
- Exception plan
- A replacement plan commissioned by the board after an exception; once approved, it takes over from the plan it replaces.
- Work package
- The agreed bundle of work and constraints handed by the project manager to a team manager.
- Quality criteria
- Measurable definitions of acceptability written into a product description before work starts.
- Quality register
- The running record of planned and completed quality activities and their results.
- Threat and opportunity
- The two faces of risk: an uncertain event with negative impact (threat) or positive impact (opportunity).
- Risk response
- The chosen action on a risk - threats: avoid, reduce, transfer, accept, contingent plans; opportunities: exploit, enhance, share, reject.
- Risk appetite
- How much risk the organisation is prepared to take; frames the project's risk tolerances.
- Risk register
- The formal record of identified risks, their assessment, responses and owners.
- Issue
- Something that has already happened and needs management attention - unlike a risk, which is uncertain.
- Request for change
- An issue proposing a change to a baseline, decided through change control.
- Off-specification
- Something that should be delivered but does not (or will not) meet specification; accepting it unchanged is a concession.
- Issue register
- The formal record of issues being managed, with their status and decisions.
- Daily log
- The project manager's informal notebook for actions and minor matters needing no formal register.
- Tolerance
- The permitted deviation around a plan's targets before escalation is required.
- Exception
- The situation where a tolerance is forecast to be exceeded, triggering escalation to the next level.
- Checkpoint report
- Team manager's progress report to the project manager, at the frequency agreed in the work package.
- Highlight report
- Project manager's periodic progress report to the project board during a stage.
- Exception report
- Project manager's report to the board on a forecast tolerance breach: situation, options, recommendation.
- End stage report
- Project manager's report to the board on a stage's performance, prepared at the stage boundary.
- Project brief
- Startup product giving the board just enough - outline business case, approach, team - to authorise initiation.
- Project initiation documentation (PID)
- The assembled definition of how the project will be managed: approaches, controls, plans, refined business case.