Cheat Sheet · Project Management

PRINCE2 7 Practitioner Cheat Sheet

intermediate

A free PRINCE2 7 Practitioner cheat sheet: the seven principles as decision tests, practices, processes, roles, reports and the exception chain.

By The Exam Atlas Editorial Team · Verified 2026-08-05

A final-revision summary of PRINCE2 7 at Practitioner level. The exam is open book (official manual only), so use this page two ways: revise from it, and copy its structure into the tabs you put in your manual.

The exam in numbers

56 questions and sub-questions · 70 marks · 150 minutes · pass mark 60% (42 marks) · open book (official PRINCE2 manual) · web-based proctored. Roughly two minutes per mark: answer from knowledge, confirm from the book.

Five integrated elements

People · Principles · Practices · Processes · Project context. Scenarios test them together - a single question can touch a practice, a principle and a role at once.

Seven principles as decision tests

PrincipleAsk of any scenario action
Ensure continued business justificationIf justification is gone, is someone escalating - or pushing on?
Learn from experienceAre lessons sought at start, recorded during, passed on at close?
Defined roles, responsibilities and relationshipsDoes everyone know who directs, who manages, who delivers?
Manage by stagesIs the board committing one stage at a time, reviewing at boundaries?
Manage by exceptionAre tolerances set, and escalation only on a forecast breach?
Focus on productsAre products and quality criteria agreed before activity planning?
Tailor to suit the projectIs the method proportionate - without dropping any principle?

Seven practices - what scenarios test

PracticeWatch for
Business caseOutput → outcome → benefit (+ dis-benefits); senior user owns benefit realisation
OrganizingExecutive decides; assurance independent of the PM; change authority within limits
PlansProduct-based planning: products and descriptions before activities; exception plan replaces stage plan
QualityQuality criteria live in product descriptions; quality register tracks activities and results
RiskUncertain = risk; responses for threats (avoid, reduce, transfer, accept, contingent plans) and opportunities (exploit, enhance, share, reject)
IssuesHappened = issue: request for change, off-specification, problem or concern; changes go through change control
ProgressTolerances per level; checkpoint, highlight, end stage and exception reports on the right routes

Seven processes (in flow)

  1. Starting up a project - executive and PM appointed; project brief; is initiation worth funding?
  2. Directing a project - the board’s process: authorise initiation, project, each stage, closure; ad-hoc direction
  3. Initiating a project - assemble the PID: approaches, controls, plans, refined business case
  4. Controlling a stage - PM’s home process: authorise work packages, manage issues and risks, report highlights
  5. Managing product delivery - team manager: accept work package, build to descriptions, checkpoint reports
  6. Managing a stage boundary - end stage report, updated business case and project plan, next stage plan (or exception plan)
  7. Closing a project - confirm acceptance, hand over, lessons, closure recommendation; the board authorises closure

The exception chain

Tolerance set → deviation forecast → issue raised → exception report (PM → board) → board decides → exception plan replaces the stage plan. Team managers escalate to the PM; only the PM escalates to the board.

Reports and their routes

ReportFrom → toWhen
CheckpointTeam manager → project managerFrequency set in the work package
HighlightProject manager → project boardTime-driven, per stage agreement
End stageProject manager → project boardAt each stage boundary
ExceptionProject manager → project boardTolerance forecast to be exceeded

Performance aspects (tolerances set on each)

Benefits · Cost · Time · Quality · Scope · Risk · Sustainability (new emphasis in PRINCE2 7).

Tailoring: allowed vs never

Allowed: combining roles (e.g. executive + senior user, PM + team manager), lighter reports and registers, merged stages on small projects. Never: dropping a principle, skipping a process entirely, executive doubling as PM, assurance delegated to the PM.

Manual tabbing checklist

Tab before exam day: each principle · each practice · each process · roles and responsibilities · management product descriptions. If a lookup takes over a minute, add another tab.

FAQ

Can I bring a cheat sheet into the PRINCE2 Practitioner exam?
No. The exam is open book, but the permitted reference is the official PRINCE2 manual under PeopleCert's exam rules - not your own notes. Use this sheet for revision and to plan how you tab the manual.
What do the exam numbers look like?
56 questions and sub-questions worth 70 marks in 150 minutes, pass mark 60% (42 marks), delivered as a web-based proctored exam. Only the PRINCE2 7 version is examinable.