Practice questions
PRINCE2 Foundation (PeopleCert): Practice Questions
Ten original concept-check questions on PRINCE2 Foundation ideas. Choose an answer to reveal the explanation. Base your reasoning on the method's structure.
-
How many principles does PRINCE2 define?
Correct answer: C. PRINCE2 has seven principles, the non-negotiable rules every PRINCE2 project must follow. -
The principle 'continued business justification' means a project should:
Correct answer: B. A PRINCE2 project must remain justified throughout; if the business case is no longer valid, it should be stopped. -
'Manage by exception' means:
Correct answer: B. Managers are given tolerances; they escalate to the next level only when those tolerances are forecast to be breached. -
Which of these is a PRINCE2 theme (an aspect managed throughout the project)?
Correct answer: B. Risk is one of the PRINCE2 themes (alongside business case, organisation, quality, plans, change and progress). -
Which PRINCE2 process begins a project, before full initiation?
Correct answer: B. 'Starting up a Project' is the pre-project process that checks the project is viable and worthwhile before initiation. -
In PRINCE2, 'tolerance' is:
Correct answer: B. Tolerances are the allowable deviations (time, cost, scope, quality, risk, benefit) before exceptions are escalated. -
PRINCE2 is best described as:
Correct answer: B. PRINCE2 is a process-based method built on principles, themes and processes, designed to be tailored to each project. -
Who is accountable for directing the project?
Correct answer: B. The project board directs the project; the project manager manages it day to day within the board's tolerances. -
The principle 'focus on products' means PRINCE2 plans are based on:
Correct answer: B. PRINCE2 is product-based: you define the products and their quality first, then the work needed to create them. -
Tailoring PRINCE2 means:
Correct answer: B. Tailoring adapts the method to the project; the seven principles, however, are always applied.