Practice questions

PMP — Project Management Professional (PMI): Practice Questions

By The Exam Atlas Editorial Team · Verified 2026-05-31

A dozen original concept-check questions on core PMP ideas. Pick an answer to reveal the explanation. These build judgement, not memorisation.

  1. A team member keeps missing deadlines because they lack a needed skill. What should the project manager do FIRST?

  2. Roughly what share of the PMP exam reflects agile or hybrid ways of working?

  3. Which of these is a risk response strategy for a THREAT (a negative risk)?

  4. A Cost Performance Index (CPI) of 0.9 indicates the project is:

  5. Who is primarily responsible for identifying project risks?

  6. A Work Breakdown Structure (WBS) is:

  7. The critical path of a project is:

  8. Servant leadership means the project manager primarily:

  9. A key stakeholder objects to a recent change. What should the project manager do FIRST?

  10. A Schedule Performance Index (SPI) of 0.8 indicates the project is:

  11. In agile delivery, who is responsible for ordering the product backlog?

  12. When a change request arrives mid-project, the project manager should:

Sources