Practice questions
CAPM (PMI): Practice Questions
Ten original concept-check questions on core CAPM ideas. Choose an answer to reveal the explanation.
-
CAPM eligibility requires:
Correct answer: B. CAPM has no work-experience requirement — only 23 hours of project management education, which PMI's free course provides. -
A project is best defined as:
Correct answer: B. Projects are temporary (defined start and end) and create something unique, unlike ongoing operations. -
A predictive (waterfall) approach is most suitable when:
Correct answer: B. Predictive approaches plan scope, schedule and cost up front and suit stable, well-understood requirements. -
A Work Breakdown Structure (WBS) is:
Correct answer: B. The WBS breaks the total scope into progressively smaller, manageable deliverables and work packages. -
A milestone in a project schedule is:
Correct answer: B. A milestone marks a significant point or event (such as a phase completion) and has no duration itself. -
Agile approaches deliver value by:
Correct answer: B. Agile delivers incrementally in short iterations, inspecting and adapting based on feedback. -
A stakeholder is:
Correct answer: B. Stakeholders include anyone affected by or able to influence the project, not just sponsors or the team. -
A project baseline is:
Correct answer: B. A baseline is the approved version of a plan used as the reference point to measure and control performance. -
The difference between iterative and incremental delivery is that incremental delivery:
Correct answer: B. Incremental delivery ships working pieces of the product over time; iterative delivery repeats cycles to refine it. Agile often combines both. -
Tailoring a project approach means:
Correct answer: B. Tailoring adapts the method and processes to fit the specific project rather than applying everything by default.